codex a272f5fcda Advance CUST-WP-0025: close T16/T17, add canon and fin-hub bootstrap
- Mark T16/T17 done with cutover evidence and decision coupling doc
- Add business-model-canvas and bootstrap-protocol canon (T20/T21)
- Record Core Hub readiness-summary evidence stubs
- Refresh fos-hub-bootstrap-sequence-status and core-hub-replacement-evidence
2026-07-08 00:52:17 +02:00

2.6 KiB
Raw Blame History

FOS Hub Bootstrap Sequence Status

Updated: 2026-07-08

Purpose

Track CUST-WP-0051-T07 and CUST-WP-0052: sequence CUST-WP-0025 so FOS Hub bootstrap can resume from current repo reality rather than the older mega-hub/Keycloak/Inter-Hub assumptions.

Current Decision

Do not restart FOS bootstrap at the old NK-WP-0001 Keycloak path. That workplan is archived and superseded. The active identity baseline is:

  • NK-WP-0002 local identity: complete; usable for bootstrap/dev OIDC.
  • NK-WP-0012 IAM Profile v0.2: finished; canonical NetKingdom-owned profile and conformance suite.
  • KeyCape/Authelia/LLDAP stack from the superseding NetKingdom path: current lightweight identity mode.
  • NK-WP-0011 expanded-mode Keycloak: proposed enterprise federation lane, not a blocker for ops-hub bootstrap.

Sequence Board

Area Current state Pickup action
Identity T01 cancelled; T02T04 done; IAM Profile integration template in core-hub. No further identity gates unless production issuer wiring is needed.
Hub extraction/dev-hub T05T12 done: hub-core exists, State Hub imports hub-core, MCP naming is dev-hub. Phase 2 complete.
Ops hub / Core Hub T13T18 done; T16 deployed evidence and T17 cutover coupling closed 2026-07-08. Production serves Core Hub at hub.coulomb.social since 2026-07-03. Monitor CORE-WP-0007 stabilization window; Haskell retirement is operator-gated rollback cleanup only.
Legacy Inter-Hub CUST-WP-0047-T05 and CUST-WP-0049-T06 superseded 2026-07-03. Rollback-only; do not request new Inter-Hub operator keys.
Fin hub/business T20T23 done (canon + fin-hub scaffold + models). T24T26 remain open. Implement cost ingestion, runway calculator, cross-hub coupling, and pricing/legal packaging.

Stable Pickup Order

  1. Close identity drift — done.
  2. Core Hub deployed evidence and cutover coupling — done (docs/core-hub-cutover-decision-coupling.md).
  3. Supersede legacy Inter-Hub waits — done 2026-07-03.
  4. Execute fin-hub implementation: T24 (cost tracking + runway), T25 (cross-hub coupling), T26 (pricing/legal).
  5. Close CORE-WP-0007 Haskell retirement after stabilization sign-off (operator gate).

Progress Summary (2026-07-08)

CUST-WP-0025 is 22/26 tasks done. Remaining:

  • T24 — fin-hub cost ingestion and runway calculator
  • T25 — fin→dev, fin→ops, fin→canon cross-hub coupling
  • T26 — RaaS pricing, onboarding, legal framework

FOS maturity: Level 2→3 boundary achieved (dev, ops, fin conceptually separated; fin-hub scaffold operational).