# FOS Hub Bootstrap Sequence Status
Updated: 2026-06-27
## Purpose
Track `CUST-WP-0051-T07`: sequence `CUST-WP-0025` so FOS Hub bootstrap can resume from current repo reality rather than the older mega-hub/Keycloak assumptions.
## Current Decision
Do not restart FOS bootstrap at the old `NK-WP-0001` Keycloak path. That workplan is archived and superseded. The active identity baseline is:
- `NK-WP-0002` local identity: complete; usable for bootstrap/dev OIDC.
- `NK-WP-0012` IAM Profile v0.2: finished; canonical NetKingdom-owned profile and conformance suite.
- KeyCape/Authelia/LLDAP stack from the superseding NetKingdom path: current lightweight identity mode.
- `NK-WP-0011` expanded-mode Keycloak: proposed enterprise federation lane, not a blocker for ops-hub bootstrap.
## Sequence Board
| Area | Current state | Pickup action |
| --- | --- | --- |
| Identity | Old `CUST-WP-0025-T01` pointed at archived `NK-WP-0001`; local identity and IAM Profile v0.2 are done. | Keep T01 cancelled, T02 done, and make T03 the remaining identity gate: a protected FastAPI fixture using IAM Profile v0.2 against local-identity or KeyCape. |
| Hub extraction/dev-hub | `CUST-WP-0025-T05` through `T12` are done: hub-core exists, State Hub imports hub-core, and MCP naming moved to dev-hub. | Treat Phase 2 as complete. Do not spend pickup energy here unless consistency drift appears. |
| Ops hub | The `ops-hub` repo exists as an Inter-Hub Operations extension. `OPS-WP-0001` is finished; `OPS-WP-0002` has T01-T03 done and waits on authenticated bootstrap/runtime key. | Finish the Inter-Hub evidence lane first: align the activity-core mapping with the live ops vocabulary, run attended bootstrap, store runtime key by approved route, then send the first governed ops event. |
| Old ops-hub scaffold tasks | `CUST-WP-0025-T13`-`T19` still describe a standalone hub-core/FastAPI/MCP scaffold. Current implementation direction is Inter-Hub extension-first. | Reconcile these tasks after the Inter-Hub evidence lane closes: either rewrite them to extension-owned implementation tasks or explicitly defer the standalone hub-core service. |
| Fin hub/business | `CUST-WP-0025-T20`-`T26` are all todo and depend on a proven multi-hub pattern. | Defer until ops-hub has a working first signal and the identity integration gate is proven. |
## Stable Pickup Order
1. Close the identity drift: T01 cancelled, T02 done, T03 remains as the one real identity integration test.
2. Finish `CUST-WP-0051-T03` / ops-hub Inter-Hub evidence alignment before expanding ops-hub models/tools.
3. Reconcile `CUST-WP-0025-T13`-`T19` against `OPS-WP-0002` once the first ops event lands.
4. Start fin-hub/business work only after ops-hub proves the extension pattern end-to-end.